General Information
Sector
Air quality
Sponsor
CEMEX Concretos SA de CV
Benefited population
1,540,072
Certification date
July 24,2009
Financing
Project cost
US 125.46M
NADBank Funds
US 102.04M - NADBank Loan
Related documents
Project Scope
The project consisted of the rehabilitation of 160 km (100 miles) of primary roadways within the municipality. The work included rehabilitating current asphalt roadways with cement concrete using the whitetopping paving technique, as well as construction or reconstruction of curbs and sidewalks, rehabilitation of storm drains and the restoration of landscaping adjacent to the roadways.