San Luis Rio Colorado, Sonora, Mexico

San Luis Rio Colorado, Sonora, Mexico

Construction of a Wastewater Treatment Plant and Rehabilitation of the Wastewater Collection System San Luis Río Colorado,Sonora

Project Status: Completed

Datos Generales

General Information

Sector

Water

Sponsor

Ayuntamiento de San Luis Rio Colorado Son.

Certification date

June 22,2000

Financiamiento

Financing

Project cost

US 16.75 million

NADBank Funds

US 7.42 million - NADBank Loan US 5.94 million - NADBank Grant: BEIF

Documentos relacionados

Related documents

The project consists of constructing a wastewater treatment plant with a capacity of 9.1 mgd (400 l/s); rehabilitation and expansion of an existing pump station, as well as the addition of a new one; and, rehabilitation and expansion of the wastewater collection system.