Rehabilitation of the Collector Poniente Tijuana, Baja California

Project Status: Completed

Datos Generales

General Information

Sector

Wastewater

Sponsor

Municipal water utility, CESPT

Benefited population

86,950

Certification date

November 9,2017

Financiamiento

Financing

Project cost

US 2.90M

NADBank Funds

US 1.41M - NADBank Grant: BEIF

Documentos relacionados

Related documents

Background

The purpose of the Project is to eliminate exposure to untreated or inadequately treated wastewater discharges by replacing deteriorated wastewater infrastructure prone to leaks and failures, and thus contribute to the reduction of water pollution and the risk of waterborne diseases.

Description

The proposed project consists of the rehabilitation of part of a collector main known as the Collector Poniente, as well as the replacement of a few related sub-collectors, in the northwestern area of Tijuana, Baja California (the “Project”).

Benefits

The environmental and human health outcomes anticipated as a result of the Project include:

• Improve wastewater collection and conveyance infrastructure for up to 23,500 existing residential wastewater connections.

• Eliminate approximately 177 liters per second (lps) or 4 million gallons per day (mgd) of untreated or inadequately treated discharges.

• Reduce the risk of line failures resulting in untreated or inadequately treated wastewater discharges to the Tijuana River, a transboundary water body.