Raymondville, Texas, USA
Raymondville, Texas, USAWater Treatment Plant for the city of Raymondville, Texas
Project Status: Completed

General Information
Sector
Water
Sponsor
City of Raymondville
Benefited population
10,774
Certification date
October 16,2001
Financing
Project cost
US 7.71 million
NADBank Funds
US 4.75 million - NADBank Grant: BEIF
Related documents
Background
The city of Raymondville currently operates a water treatment plant built over 60 years ago, with an original treatment capacity of 0.75 million gallons per day (mgd). Over the years, the city has expanded the plant to a current capacity of 2.5 mgd.
The plant is at 95 percent of its capacity of 2.5 mgd during non-peak periods; however demand during peak periods has exceeded 2.8 mgd, creating a serious risk for potential contamination of the water supply. Thus, the Texas Commission on Environmental Quality (TCEQ) has cited the city for operating its water treatment plant above capacity at
times and issued an enforcement order requiring the city to replace the plant.
Description
Replacement of the water treatment plant includes the following
components:
- Construction of a 4.5 mgd water treatment plant.
- Demolition of the existing plant.
- Construction of a high service pump station.
- Construction of a 500,000 gallon ground storage tank.
- Construction of a new 16” water transmission line to tie into the
existing distribution system.
Benefits
With the construction of this new water treatment plant, the residents of Raymondville will have access to a safe, dependable supply of potable water able to meet current and future community demand.