Douglas, Arizona, USA
Douglas, Arizona, USAWater and Wastewater System Improvements Project in Douglas, Arizona
Project Status: Completed

General Information
Sector
Water and wastewater
Sponsor
City of Douglas
Benefited population
18,000
Certification date
June 20,2001
Financing
Project cost
US 7.08M
NADBank Funds
US 3.67M - NADBank Grant: BEIF
Related documents
Background
In 2001, the drinking water and wastewater collection systems serving the residents of Douglas had exceeded their useful life and were significantly deteriorated. In addition to insufficient coverage and failing septic tank systems, approximately 30% of the wastewater collection system was deficient due to leaks or overloaded lines, while 18,160 feet of sewer lines had flow velocities of less than two feet per second, allowing solids to accumulate and clog the pipes. Improvements needed in the water distribution system included a new pressure zone to serve residents of east Van Buren Avenue and new transmission lines to convey water to the Fairview and Pirtleville colonias.
Project Scope
Water system improvements consisted of constructing 55,795 linear feet of distribution lines, as well as rehabilitating a booster station and a pressure reducing station. Wastewater system improvements included the construction of 83,770 linear feet of sewer lines and more than 170 manholes and fittings.
Benefits
The project provided a healthier environment for all residents of Douglas and the surrounding colonias by eliminating untreated sewage discharges from broken sewer lines. In addition, rehabilitating the distribution system and providing a new pressure zone improved the delivery and quality of drinking water and reduced water losses from leaky waterlines.